MARINE NOTICE, No 007 of 2017

Map Inland Waterways Ireland
Inland Waterway’s, © WI

MARINE NOTICE, No 7 of 2017

BOAT PASSAGE IN and OUT OF DUBLIN 2017

ROYAL AND GRAND CANALS

Waterways Ireland wish to remind masters and owners of boat passage arrangements for movements in or out of Dublin on the Royal & Grand Canals in 2017. Movements in or out of the city will be organised by prior arrangement to take place as a single movement in one day. Boaters will be facilitated to travel the system if their passage is considered to be safe by Waterways Ireland and they have the valid permit(s) for mooring and passage.

For boat passage through the locks east of Lock 12 into / out from Dublin on either the Royal or Grand Canals, Masters are requested to contact the Waterways Ireland Eastern Regional Office (M-F 9.30am-4.30pm) on tel: + +353-(0)1-868-0148 or email dublincanals@waterwaysireland.org prior to making passage in order to plan the necessary lock-keeping assistance arrangements.

On the Grand Canal a minimum of two days notice prior to planned passage must be given and, with the exception of pre-arranged events, a maximum of 2 boats per day will be taken through the locks, travelling either east or west. In certain circumstances, e.g. for slower or larger barges, the limit will be 1 boat per day. Due to periodic anti-social activity along some of canal route into Dublin, boat passage will also not be possible in certain weather conditions and at weekends over the late spring & summer period. This can be planned for at time of making contact, and suitable arrangements for passage made.

On the Royal Canal two weeks’ notice of bridge passage (Newcomen Lifting Bridge) is required for the pre-set lift date, and lock assistance will then also be arranged. A minimum of 2 boats is required for a bridge lift to go ahead; please have available length, beam, water & air drafts of your craft, and phone / email details at time of making contact. The pre-set lift dates are set out in MN 6 of 2017.

Masters and owners are also reminded to ensure they have the following before making the passage through the city locks on both canals:

    • adequate fuel on board
    • competent and adequate crew to operate the boat and locks (minimum crew of 3)
    • a lock key on board their boat
    • mooring lines of adequate length to handle vessel through a lock (approx 15m length)
    • no known mechanical problems with their boat

Passages can be arranged in the boating season from mid-March to end of October; however note that aquatic weed is generally more prevalent as the season progresses beyond Spring and may hamper passage. Boaters will be facilitated as far as practicable although Waterways Ireland cannot guarantee that passage will be possible on every planned date. Early contact will greatly assist planning and facilitate the making of the necessary arrangements.

C.J.Lawn,Inspector of Navigation, 7 Feb 2017

Schreibe einen Kommentar