MARINE NOTICE, No. 65 of 2022

 Athlone Lock © esri; click picture to esri maps " Athlone Lock © esri"
Link to Athlone Lock © esri

MARINE NOTICE, No. 65 of 2022

Shannon Navigation

Athlone

Construction of pedestrian and cycleway bridge

Update on works

Waterways Ireland wishes to advise all masters of vessels and waterways users that the construction of the Athlone pedestrian and cycleway bridge commenced on 03 May 2022. The pedestrian and cycleway bridge will be built approx. 50 metres upstream of Athlone town bridge.
The navigation channel in the vicinity of the in-water works will continue to be restricted during the works. Large barges, workboats and other equipment will be operating in the navigation from Wansboro’s field (upstream of the Railway Bridge) to Athlone town bridge. Update on each Phase of the project is provided below.
Masters of vessels are advised to proceed with additional caution in the vicinity of the works and to follow the instructions of safety craft and personnel in the area.
Waterways Ireland thanks its customers for their cooperation.
Text Description automatically generated

P Harkin, Inspector of Navigation, 28 June 2022

Phase 1
Phase 1Installation of centre pier cofferdam. 15-18m Navigation Channel along West Bank

Phase2  Phase 2Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 3
Phase 3Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 4
Phase 4Installation of centre bridge section Late-August. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 5
Phase 5
Installation of Eastern bridge section approx. Early September. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 6
Phase 6Installation of Western bridge section approx. Mid-September. Approx. duration of 3-4 days. Navigation Channel reduced to 10 – 12 metres adjacent to Centre Pier. One way system in operation for vessels.

Phase 7
Phase 7
Removal of temporary works from instream. Approx 1 week duration at end of September / early October. Open permanent 40 metre Navigation Channel along West Bank.

Athlone, Bau einer Fußgänger- und Radwegbrücke, Aktueller Stand der Arbeiten
Waterways Ireland möchte alle Schiffskapitäne und Wasserstraßennutzer darüber informieren, dass die Bauarbeiten für die Fußgänger- und Radwegbrücke in Athlone am 03. Mai 2022 begonnen haben. Die Fußgänger- und Radwegbrücke wird ca. 50 Meter stromaufwärts der Athlone Stadtbrücke gebaut.
Die Schifffahrtsrinne in der Nähe der Unterwasserarbeiten wird während der Arbeiten weiterhin eingeschränkt sein. Große Lastkähne, Arbeitsboote und andere Geräte werden in der Fahrrinne von Wansboro’s Field (flussaufwärts der Eisenbahnbrücke) bis zur Athlone Town Bridge verkehren. Im Folgenden finden Sie aktuelle Informationen zu den einzelnen Phasen des Projekts.
Die Kapitäne der Schiffe werden gebeten, in der Nähe der Arbeiten besonders vorsichtig zu fahren und den Anweisungen der Sicherheitsfahrzeuge und des Personals in diesem Gebiet Folge zu leisten.
Waterways Ireland dankt seinen Kunden für ihre Mitarbeit.
Text Beschreibung automatisch generiert

    • Phase 1
      Einbau eines Kofferdamms für die Mittelmole. 15-18m Schifffahrtskanal entlang des Westufers
    • Phase 2
      Provisorische Stützen und Mittelmole in Position ab Mitte Juli. Reduzierung der Fahrrinne auf ca. 15 m
    • Phase 3
      Temporäre Stützen und Mittelpfeiler ab Mitte Juli in Position. Verringerung der Fahrrinne auf ca. 15 m
    • Phase 4
      Einbau des mittleren Brückenteils Ende August. Dauer: ca. 3-4 Tage. Beibehaltung der 12-15 m breiten Fahrrinne am Westufer
    • Phase 5
      Einbau des östlichen Brückenteils ca. Anfang September. Dauer: ca. 3-4 Tage. Aufrechterhaltung der 12-15 m langen Fahrrinne entlang des Westufers
    • Phase 6
      Einbau des westlichen Brückenteils ca. Mitte September. Dauer: ca. 3-4 Tage. Verkleinerung der Fahrrinne auf 10 – 12 Meter neben der Mittelmole. Einbahnregelung für Schiffe in Betrieb.
    • Phase 7
      Beseitigung der provisorischen Arbeiten im Fluss. Ca. 1 Woche Dauer Ende September/Anfang Oktober. Eröffnung der permanenten 40 Meter langen Fahrrinne entlang des Westufers.

MARINE NOTICE, No 30. of 2022

 Athlone Lock © esri; click picture to esri maps " Athlone Lock © esri"
Link to Athlone Lock © esri

MARINE NOTICE, No 30. of 2022

Shannon Navigation Athlone

Construction of pedestrian and cycleway bridge
Commencing on 03 May 2022

Waterways Ireland wishes to advise all masters of vessels and waterways users that the construction of the Athlone pedestrian and cycleway bridge will commence on 03 May 2022. The pedestrian and cycleway bridge will be built approx. 50 metres upstream of Athlone town bridge.
The navigation channel in the vicinity of the in-water works will be restricted to a width of 15 metres from 03 May 2022. Both sides of the navigation channel will be buoyed with temporary makers. Large barges, workboats and other equipment will be operating in the navigation from Wansboro’s field (upstream of the Railway Bridge) to Athlone town bridge.
Masters of vessels are advised to proceed with additional caution in the vicinity of the works and to follow the instructions of safety craft and personnel in the area.
Phase 1 of the project commencing on 03 May 2022 involves the installation of a cofferdam which will take approx. 4 weeks to complete. Details of further phases will be advised in due course.
Waterways Ireland thanks its customers for their cooperation.

Phase 1

Phase 1 Centre Pier Cofferdam
Phase 1 Centre Pier Cofferdam; © WI

Installation of centre pier cofferdam. Approx. duration of 4 weeks commencing from 3rd May – Maintain 15-18m Navigation Channel along West Bank

Phase 2

Phase 2 Temp Supports and Centre Pier in Position; © WI
Phase 2 Temp Supports and Centre Pier in Position; © WI

Temporary supports and centre pier in position from Mid-July – Navigation Channel reduced to approx. 15m

Paddy Harkin, Cdr (Rtd), Inspector of Navigation, Waterways Ireland, The Docks, Athlone, Co Westmeath, 08 April 2022

Athlone Shannon
Bau einer Fußgänger- und Radwegbrücke; Baubeginn am 03. Mai 2022
Waterways Ireland möchte alle Schiffskapitäne und Wasserstraßennutzer darauf hinweisen, dass am 3. Mai 2022 mit dem Bau der Fußgänger- und Radwegbrücke in Athlone begonnen wird. Die Fußgänger- und Radwegbrücke wird ca. 50 Meter stromaufwärts der Athlone Stadtbrücke gebaut.
Die Fahrrinne in der Nähe der Bauarbeiten wird ab dem 03. Mai 2022 auf eine Breite von 15 Metern beschränkt. Beide Seiten der Fahrrinne werden mit provisorischen Bojen versehen. Große Lastkähne, Arbeitsboote und andere Ausrüstungen werden in der Fahrrinne von Wansboro’s Field (stromaufwärts der Eisenbahnbrücke) bis zur Athlone Town Bridge verkehren.
Die Kapitäne von Schiffen werden gebeten, in der Nähe der Arbeiten besonders vorsichtig zu fahren und den Anweisungen der Sicherheits-fahrzeuge und des Personals in diesem Gebiet Folge zu leisten.
Phase 1 des Projekts, die am 03. Mai 2022 beginnt, umfasst die Errichtung eines Fangedamms, die ca. 4 Wochen in Anspruch nehmen wird. Einzelheiten zu den weiteren Phasen werden zu gegebener Zeit bekannt gegeben.
Waterways Ireland dankt seinen Kunden für ihre Mitarbeit.

Phase 1
Einbau des Kofferdamms für die Mittelmole. Dauer ca. 4 Wochen, beginnend am 3. Mai – Aufrechterhaltung der 15-18 m breiten Fahrrinne am Westufer

Phase 2
Temporäre Stützen und Mittelmole in Position ab Mitte Juli – Reduzierung der Fahrrinne auf ca. 15 m