MARINE NOTICE, No. 24 of 2023

Barrow navigations; Link to Tinnahinch;© esri
Barrow navigations; Tinnahinch;© esri

MARINE NOTICE, No. 24 of 2023

Barrow Navigation

Tinnahinch

Barrow Way Closure, 28 March to 7 April 2023

Waterways Ireland wishes to advise users of the Barrow Way that the trackway section from Graiguenamanagh Bridge to 100m south of Upper Tinnahinch Lock will be closed from 28th March to 7th April 2023 to accommodate the County Council undertake Site Investigation works for Graiguenamanagh / Tinnahinch Flood Relief Scheme.

Closure Details as follows:

      • 08:00hrs to 17:00hrs – No Public Access
      • 17:00hrs to 08:00hrs – Restricted Public Access
      • Local property access will be accommodated.

Waterways Ireland thanks its customers for their understanding in relation to this matter.

Patrick Harkin, Inspector of Navigation, 28 March 2023

Barrow below Lower Tinnahinch Lock
Barrow above Lower Tinnahinch Lock
Barrow below Lower Tinnahinch Lock
Barrow below Lower Tinnahinch Lock

Barrow Navigation, Tinnahinch
Barrow Way Sperrung, 28. März bis 7. April 2023
Waterways Ireland möchte die Nutzer des Barrow Way darauf hinweisen, dass der Streckenabschnitt von der Graiguenamanagh Bridge bis 100 m südlich der Upper Tinnahinch Lock vom 28. März bis zum 7. April 2023 gesperrt wird, um dem County Council die Möglichkeit zu geben, Arbeiten zur Untersuchung des Geländes für das Graiguenamanagh/Tinnahinch Flood Relief Scheme durchzuführen.
Details der Schließung wie folgt:

      • 08:00 Uhr bis 17:00 Uhr – Kein öffentlicher Zugang
      • 17:00 Uhr bis 08:00 Uhr – Eingeschränkter Zugang für die Öffentlichkeit
      • Der Zugang zu lokalen Grundstücken wird gewährleistet.

Waterways Ireland dankt seinen Kunden für ihr Verständnis in dieser Angelegenheit.