MARINE NOTICE, No. 80 of 2022

Shannon Navigation

Athlone, Construction of pedestrian and cycleway bridge

Update on works

Waterways Ireland wishes to update all masters of vessels and waterways users on the construction of the pedestrian and cycleway bridge in Athlone.
The navigation channel in the vicinity of the works will continue to be restricted until end of September 2022.
On Tuesday 30th and Wednesday 31st August 2022 the first section of bridge will be floated downstream from Wansboro’s field on an 18m x 18m sized pontoon. Two tugs will be manoeuvring the pontoon. Two safety boats will be on the river during the bridge moving operation.
In preparation for the bridge moving operation, the three up-stream sections of the new Waterways Ireland jetty at the Railway Bridge will be removed from Thursday 25th August 2022. All power and water to the remaining sections of the jetty will be disconnected for safety reasons from 25th August 2022. The red navigation markers at the railway bridge will also be removed.
No vessel will be allowed to moor on the Waterways Ireland jetty at the Railway Bridge from 2000hrs on Mon 29th August until 2000hrs on Wednesday 31st August 2022.
Masters of vessels are advised to proceed with additional caution in the vicinity of the works and to follow the instructions of safety craft and personnel in the area.
Waterways Ireland thanks its customers for their cooperation.
Text Description automatically generated

P Harkin, Inspector of Navigation, 08 August 2022

Phase 4Phase 4Installation of centre bridge section 30th – 31st August. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 5
Phase 5
Installation of Eastern bridge section approx. Early September. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 6
Phase 6
Installation of Western bridge section approx. Mid-September. Approx. duration of 3-4 days. Navigation Channel reduced to 10 – 12 metres adjacent to Centre Pier. One way system in operation for vessels.

Phase 7
Phase 7
Removal of temporary works from instream. Approx 1 week duration at end of September / early October. Open permanent 40 metre Navigation Channel along West Bank.

Athlone, Bau einer Fußgänger- und Radwegbrücke, Aktueller Stand der Arbeiten
Waterways Ireland möchte alle Schiffskapitäne und Wasserstraßenbenutzer über die Bauarbeiten an der Fußgänger- und Radwegbrücke in Athlone informieren.
Die Fahrrinne in der Nähe der Bauarbeiten wird bis Ende September 2022 gesperrt bleiben.
Am Dienstag, den 30. und Mittwoch, den 31. August 2022 wird das erste Brückenteil stromabwärts vom Wansboro’s Field auf einem 18 m x 18 m großen Ponton zu Wasser gelassen. Zwei Schlepper werden den Ponton manövrieren. Zwei Sicherheitsboote werden während des Brückenumzugs auf dem Fluss sein.
In Vorbereitung der Brückenverlegung werden die drei stromaufwärts gelegenen Abschnitte des neuen Waterways Ireland Stegs an der Eisenbahnbrücke ab Donnerstag, den 25. August 2022, entfernt. Die Strom- und Wasserzufuhr zu den verbleibenden Abschnitten der Anlegestelle wird aus Sicherheitsgründen ab dem 25. August 2022 unterbrochen. Die roten Schifffahrtsmarkierungen an der Eisenbahnbrücke werden ebenfalls entfernt.
Von Montag, dem 29. August, 2000 Uhr, bis Mittwoch, dem 31. August 2022, 2000 Uhr, dürfen keine Schiffe an der Waterways Ireland-Anlegestelle an der Eisenbahnbrücke anlegen.
Den Schiffsführern wird empfohlen, in der Nähe der Bauarbeiten besonders vorsichtig zu sein und den Anweisungen der Sicherheitsfahrzeuge und des Personals in diesem Bereich Folge zu leisten.
Waterways Ireland dankt seinen Kunden für ihre Kooperation.
Text Beschreibung automatisch generiert.
Phase 4
Einbau des mittleren Brückenteils 30. – 31. August. Dauer ca. 3-4 Tage. Beibehaltung der 12-15 m breiten Fahrrinne entlang des Westufers
Phase 5
Einbau des östlichen Brückenteils ca. Anfang September. Dauer: ca. 3-4 Tage. Aufrechterhaltung der 12-15 m langen Fahrrinne entlang des Westufers
Phase 6
Einbau des westlichen Brückenteils ca. Mitte September. Dauer: ca. 3-4 Tage. Verkleinerung der Fahrrinne auf 10 – 12 Meter neben der Mittelmole. Einbahnregelung für Schiffe in Betrieb.
Phase 7
Beseitigung der provisorischen Arbeiten im Fluss. Ca. 1 Woche Dauer Ende September/Anfang Oktober. Eröffnung der permanenten 40 Meter langen Fahrrinne entlang des Westufers.

MARINE NOTICE, No. 79 of 2022 amended

Link to LDYClub have 4 sailing areas as shown on the map. © esri
Link to LDYClub have 4 sailing areas shown on the map: © esri

Marine Notice, No. 79 of 2022

Shannon Navigation

Lough Derg

World Fireball Sailing

Championships, 21 to 26 August 2022
Waterways Ireland wishes to advise masters of vessels that the World Fireball sailing championships will take place from 21 to 26 August 2022 on Lough Derg. The event will be based out of LDYClub have 4 sailing areas as shown on the map.

LDYClub have 4 sailing areas as shown on the map. © esri
LDYClub have 4 sailing areas as shown on the map. © esri click picture to enlarge

Master of vessels are requested to proceed with additional caution in the vicinity of the sailing events. Waterways Ireland thanks its customers for their cooperation in this matter.

World Fireball sailing championships on Lough Derg
Link to Sail World Fireball sailing championships on Lough Derg click picture

P Harkin, Inspector of Navigation, 08 August 2022

Shannon Navigation, Lough Derg
Weltmeisterschaften im Fireball-Segeln, 21. bis 26. August 2022
Waterways Ireland möchte die Kapitäne von Schiffen darauf hinweisen, dass vom 21. bis 26. August 2022 die Weltmeisterschaft im Fireball-Segeln auf dem Lough Derg stattfinden wird. Die Veranstaltung findet vom Lough Derg Yacht Club aus statt und hat 4 Segelgebiete, wie auf der Karte dargestellt.
Die Schiffsführer werden gebeten, in der Nähe der Segelveranstaltungen besonders vorsichtig zu sein. Waterways Ireland dankt seinen Kunden für ihre Kooperation in dieser Angelegenheit.

MARINE NOTICE, No. 78 of 2022

Mullingar Harbour © esri
Mullingar Harbour © esri

MARINE NOTICE, No. 78 of 2022

Royal Canal

Mullingar Harbour

Float to the Fleadh

31st July to 7th August 2022

mullingarfleadh  · Community
mullingarfleadh , on facebook
Waterways Ireland wishes to advise masters of vessels that the Float to the Fleadh will take place from 31st July to 7th August 2022 on the Royal Canal.
A flotilla of approx. 40 vessels will be transiting the canal and gathering in Mullingar Harbour for the duration of this event.
Masters of craft are requested to proceed at slow speed and with minimum wash while transiting the area.
Waterways Ireland thanks its customers for their co-operation in relation to this matter.

P Harkin, Inspector of Navigation, 29 July 2022

Mullingar Scanlans Bridge © A.J. Vosse
Mullingar Harbour and Scanlans Bridge © A.J. Vosse

Royal Canal, Hafen von Mullingar, Flottille zum Festival, 31. Juli bis 7. August 2022
Waterways Ireland möchte die Kapitäne von Schiffen darauf hinweisen, dass die Flottille zum Fest (Float to the Fleadh) vom 31. Juli bis 7. August 2022 auf dem Royal Canal stattfinden wird.
Eine Flottille von ca. 40 Schiffen wird den Kanal durchqueren und sich für die Dauer dieser Veranstaltung im Hafen von Mullingar versammeln.
Die Kapitäne der Schiffe werden gebeten, bei der Durchfahrt durch das Gebiet mit langsamer Geschwindigkeit und möglichst wenig Wasser zu fahren.
Waterways Ireland dankt seinen Kunden für ihre Kooperation in dieser Angelegenheit.

MARINE NOTICE, No. 77 of 2022

Lough-Ree; Hexagon Shoal; © esri
Lough-Ree; Hexagon Shoal; © esri

MARINE NOTICE, No. 77 of 2022

Shannon Navigation

Lough Ree

Hexagon Shoal

Additional navigation markers

Waterways Ireland wishes to advise masters of vessels on the Shannon Navigation that 8 small green navigation markers will be installed at the Hexagon shoal from 01 August 2022 for a trial period. Four small markers will be installed on the north side of Marker 615 and four small markers installed on the east side of Marker 615. See chartlet below.
Waterways Ireland advises boaters to always use an up-to-date Navigation Guide when boating on the Shannon Navigation.
Waterways Ireland thanks its customers for their co-operation in relation to this matter.

P Harkin, Inspector of Navigation, 28 July 2022

Hexagon Shoal, Additional green navigation markers
Hexagon Shoal, Additional green navigation markers; © esri

Lough Ree, Hexagon Shoal;  Zusätzliche Navigationsmarker
Waterways Ireland möchte die Kapitäne von Schiffen auf dem Shannon Navigation darauf hinweisen, dass ab dem 01. August 2022 probeweise 8 kleine grüne Schifffahrtszeichen an der Untiefe Hexagon installiert werden. Vier kleine Schifffahrtszeichen werden auf der Nordseite des Markers 615 und vier kleine Schifffahrtszeichen auf der Ostseite des Markers 615 installiert. Siehe nachstehendes Kartenblatt.
Waterways Ireland rät Bootsfahrern, immer einen aktuellen Navigationsführer zu benutzen, wenn sie auf dem Shannon Navigation fahren.
Waterways Ireland dankt seinen Kunden für ihre Kooperation in dieser Angelegenheit.

MARINE NOTICE, No. 76 of 2022, Updated

Richmond Harbour; © esri; clicl picture to ArcGismap Richmond Harbour
Richmond Harbour; © esri

MARINE NOTICE, No. 76 of 2022, Updated

Royal Canal

Clondra – Richmond Harbour

Canoe Polo

Saturday 30th July & Sunday 31st July 2022    Cancelled

Waterways Ireland wishes to advise all masters of vessels and users of the Royal Canal that the canoe polo competition on Saturday 30th July & Sunday 31st July 2022 has been cancelled.
Waterways Ireland takes this opportunity to thank its customers for their co-operation with these arrangements.

P Harkin, Inspector of Navigation, 27 Jul 2022

Richmond Harbour; © chb ; click picture to enlarge
Richmond Harbour; © chb ; click picture to enlarg

Royal Canal,  Clondra – Richmond Harbour – Kanu-Polo
Samstag 30. Juli & Sonntag 31. Juli 2022,   Abgesagt
Waterways Ireland möchte alle Schiffskapitäne und alle Benutzer des Royal Canal darüber informieren, dass der Kanupolo-Wettbewerb am Samstag, den 30. Juli und Sonntag, den 31. Juli 2022 abgesagt wurde.
Waterways Ireland bedankt sich bei dieser Gelegenheit bei seinen Kunden für ihre Kooperation bei diesen Veranstaltungen.