MARINE NOTICE, No. 65 of 2022

 Athlone Lock © esri; click picture to esri maps " Athlone Lock © esri"
Link to Athlone Lock © esri

MARINE NOTICE, No. 65 of 2022

Shannon Navigation

Athlone

Construction of pedestrian and cycleway bridge

Update on works

Waterways Ireland wishes to advise all masters of vessels and waterways users that the construction of the Athlone pedestrian and cycleway bridge commenced on 03 May 2022. The pedestrian and cycleway bridge will be built approx. 50 metres upstream of Athlone town bridge.
The navigation channel in the vicinity of the in-water works will continue to be restricted during the works. Large barges, workboats and other equipment will be operating in the navigation from Wansboro’s field (upstream of the Railway Bridge) to Athlone town bridge. Update on each Phase of the project is provided below.
Masters of vessels are advised to proceed with additional caution in the vicinity of the works and to follow the instructions of safety craft and personnel in the area.
Waterways Ireland thanks its customers for their cooperation.
Text Description automatically generated

P Harkin, Inspector of Navigation, 28 June 2022

Phase 1
Phase 1Installation of centre pier cofferdam. 15-18m Navigation Channel along West Bank

Phase2  Phase 2Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 3
Phase 3Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 4
Phase 4Installation of centre bridge section Late-August. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 5
Phase 5
Installation of Eastern bridge section approx. Early September. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 6
Phase 6Installation of Western bridge section approx. Mid-September. Approx. duration of 3-4 days. Navigation Channel reduced to 10 – 12 metres adjacent to Centre Pier. One way system in operation for vessels.

Phase 7
Phase 7
Removal of temporary works from instream. Approx 1 week duration at end of September / early October. Open permanent 40 metre Navigation Channel along West Bank.

Athlone, Bau einer Fußgänger- und Radwegbrücke, Aktueller Stand der Arbeiten
Waterways Ireland möchte alle Schiffskapitäne und Wasserstraßennutzer darüber informieren, dass die Bauarbeiten für die Fußgänger- und Radwegbrücke in Athlone am 03. Mai 2022 begonnen haben. Die Fußgänger- und Radwegbrücke wird ca. 50 Meter stromaufwärts der Athlone Stadtbrücke gebaut.
Die Schifffahrtsrinne in der Nähe der Unterwasserarbeiten wird während der Arbeiten weiterhin eingeschränkt sein. Große Lastkähne, Arbeitsboote und andere Geräte werden in der Fahrrinne von Wansboro’s Field (flussaufwärts der Eisenbahnbrücke) bis zur Athlone Town Bridge verkehren. Im Folgenden finden Sie aktuelle Informationen zu den einzelnen Phasen des Projekts.
Die Kapitäne der Schiffe werden gebeten, in der Nähe der Arbeiten besonders vorsichtig zu fahren und den Anweisungen der Sicherheitsfahrzeuge und des Personals in diesem Gebiet Folge zu leisten.
Waterways Ireland dankt seinen Kunden für ihre Mitarbeit.
Text Beschreibung automatisch generiert

    • Phase 1
      Einbau eines Kofferdamms für die Mittelmole. 15-18m Schifffahrtskanal entlang des Westufers
    • Phase 2
      Provisorische Stützen und Mittelmole in Position ab Mitte Juli. Reduzierung der Fahrrinne auf ca. 15 m
    • Phase 3
      Temporäre Stützen und Mittelpfeiler ab Mitte Juli in Position. Verringerung der Fahrrinne auf ca. 15 m
    • Phase 4
      Einbau des mittleren Brückenteils Ende August. Dauer: ca. 3-4 Tage. Beibehaltung der 12-15 m breiten Fahrrinne am Westufer
    • Phase 5
      Einbau des östlichen Brückenteils ca. Anfang September. Dauer: ca. 3-4 Tage. Aufrechterhaltung der 12-15 m langen Fahrrinne entlang des Westufers
    • Phase 6
      Einbau des westlichen Brückenteils ca. Mitte September. Dauer: ca. 3-4 Tage. Verkleinerung der Fahrrinne auf 10 – 12 Meter neben der Mittelmole. Einbahnregelung für Schiffe in Betrieb.
    • Phase 7
      Beseitigung der provisorischen Arbeiten im Fluss. Ca. 1 Woche Dauer Ende September/Anfang Oktober. Eröffnung der permanenten 40 Meter langen Fahrrinne entlang des Westufers.

MARINE NOTICE, No. 64 of 2022

Lough Derg IWAI Rally 2022; © esri
Lough Derg IWAI Rally 2022; © esri

MARINE NOTICE, No. 64 of 2022

Shannon Navigation

Lough Derg,

IWAI Rally,

9th to 16th July 2022

Waterways Ireland wishes to advise masters and owners of vessels that the IWAI Lough Derg Rally will take place from Sat 9th to Sun 16th Jul 2022 and will visit the following locations:

      • Saturday, July 9th, Dromann
      • Sunday, July 10th, Dromann
Dromaan-Harbour; click to map; © esri
Dromaan-Harbour; click to map; © esri
Lough Derg Dromaan neuer Service Block;  © Driftwood.TV; click picture to Driftwood.TV
Dromaan neuer Service Block; © Driftwood.TV
Hafeneinfahrt Dromaan
Hafeneinfahrt (Harbour entrance)
Hafeneinfahrt Dromaan
Hafeneinfahrt Dromaan
Picknick Platz (Picnic place)
Picknick Platz (Picnic place)
Anleger Harbour Dromaan
Anleger Harbour Dromaan

      • Monday, July 11th, Mountshannon
      • Tuesday, July 12th, Mountshannon
Mountshannon, Harbour Mooring
Mountshannon, Harbour Mooring
Mountshannon, Harbour Mooring
Mountshannon, Harbour Mooring
Mountshannon Sailing Regatta
Mountshannon Sailing Regatta
Mountshannon, Harbour Mooring
Mountshannon, Harbour Mooring
      • Wednesday, July 13th, Anchor Out
Drop anchor in the Fleet
Drop anchor in the Fleet
All boats are at anchor
All boats are at anchor
View of the stern of the boats
View of the stern of the boats
View of the bow of the boats
View of the bow of the boats
      • Thursday, July 14th, Terryglass
      • Friday, July 15th, Terryglass
      • Saturday, July 16th, Terryglass
Terryglass Harbour Floating Jetty
Terryglass Harbour Floating Jetty
Terryglass Harbour Floating Jetty
Terryglass Harbour Floating Jetty
CIC in Terryglass Harbour
CIC in Terryglass Harbour
Terryglass Harbour on the quay wall
Terryglass Harbour on the quay wall

Masters of vessels should be aware that a significant number of vessels will be participating in the rally.
Waterways Ireland thanks its customers for their cooperation in this matter.

P Harkin, Inspector of Navigation, 28 June 2022

Shannon Navigation, Lough Derg,  IWAI Rallye, 9. bis 16. Juli 2022
Waterways Ireland möchte Kapitäne und Bootsbesitzer darauf hinweisen, dass die IWAI Lough Derg Rallye vom 9. bis 16. Juli 2022 an folgenden Orten stattfinden wird:

      • Samstag, 9. Juli, Dromann
      • Sonntag, 10. Juli, Dromann
      • Montag, 11. Juli, Mountshannon
      • Dienstag, 12. Juli, Mountshannon
      • Mittwoch, 13. Juli, Ankern aussen
      • Donnerstag, 14. Juli, Terryglass
      • Freitag, 15. Juli, Terryglass
      • Samstag, 16. Juli, Terryglass

Die Kapitäne der Schiffe sollten sich bewusst sein, dass eine beträchtliche Anzahl von Schiffen an der Rallye teilnehmen wird.
Waterways Ireland dankt seinen Kunden für ihre Kooperation in dieser Angelegenheit.