MARINE NOTICE, No. 96 of 2023, UPDATED

Shannon Harbour © esri
Shannon Harbour © esri

MARINE NOTICE, No. 96 of 2023, UPDATED

Grand Canal – Shannon Harbour

Quay Wall Repair,
25th September to mid-November

Temporary Navigation markers

Waterways Ireland wishes to advise all masters of vessels and waterway users that it will be carrying out maintenance works on a damaged section of the north quay wall in Shannon Harbour.
Works will begin on Monday the 25th of September and will last approx. 7 weeks, hours of work 9am to 5pm. A section of the harbour wall will be closed off to boat users during this time.
The access road to the north of Shannon harbour will be closed to public traffic and only local traffic will be permitted.
Water Levels in Shannon Harbour may have to be lowered for a time to allow these works to be completed.
Four temporary red navigation markers are in place on the south side of the works location to aid navigation through the area.
Waterways Ireland thanks its customers for their co-operation in relation to this matter.

P Harkin, Inspector of Navigation, Waterways Ireland, 18 October 2023

Shannon Harbour Grand Canal; Captain's Handbook ©
Shannon Harbour Grand Canal; © CHB

Grand Canal – Shannon Harbour; Reparatur der Kaimauer
25. September bis Mitte November, Temporäre Navigationsmarkierungen
Waterways Ireland möchte alle Kapitäne von Schiffen und Wasserstraßenbenutzer darauf hinweisen, dass an einem beschädigten Abschnitt der nördlichen Kaimauer im Shannon Harbour Wartungsarbeiten durchgeführt werden.
Die Arbeiten beginnen am Montag, dem 25. September, und werden ca. 7 Wochen dauern, Arbeitszeiten von 9 bis 17 Uhr. Während dieser Zeit wird ein Teil der Hafenmauer für Bootsfahrer gesperrt sein.
Die Zufahrtsstraße nördlich des Shannon Harbour wird für den öffentlichen Verkehr gesperrt und nur der örtliche Verkehr wird zugelassen.
Der Wasserstand im Shannon Harbour muss unter Umständen vorübergehend gesenkt werden, damit die Arbeiten abgeschlossen werden können.
Auf der Südseite der Baustelle sind vier vorübergehende rote Schifffahrtszeichen aufgestellt, um die Navigation durch das Gebiet zu erleichtern.
Waterways Ireland dankt seinen Gästen für ihre Kooperation in dieser Angelegenheit.

MARINE NOTICE, No. 115 of 2023

LLE-Portora Lock; © esri click to Portora-Lock-Map esri"
LLE-Portora Lock; © esri

MARINE NOTICE, No. 115 of 2023

Erne System

Enniskillen

Operation of Portora Lock

Waterways Ireland wishes to advise Masters of Vessels and waterway users on the Erne System that Portora Lock is in operation. During the locks operating times, a lockkeeper will be present and will complete the operation of the lock gates.
Portora Lock operating times are as follows:

      • 8.00am to 10.30pm 7 days a week when in operation.

Waterways Ireland thanks its customers for their cooperation.

P Harkin, Inspector Of Navigation, Waterways Ireland, 18 October 2023

Portoralock closed
Portoralock closed; ©Pas Vite

Erne System, Enniskillen, Betrieb des Portora Lock
Waterways Ireland möchte die Kapitäne von Schiffen und Wasserstraßenbenutzer des Erne-Systems darauf hinweisen, dass das Portora Lock in Betrieb ist. Während der Betriebszeiten des Portora Lock ist ein Lockkeeper anwesend, der die Bedienung der Schleusentore übernimmt.
Die Betriebszeiten des Portora Lock sind wie folgt:

      • 8.00 Uhr bis 22.30 Uhr an 7 Tagen in der Woche, wenn sie in Betrieb ist.

Waterways Ireland dankt seinen Gästen für ihre Mitarbeit.