MARINE NOTICE, No. 65 of 2022

 Athlone Lock © esri; click picture to esri maps " Athlone Lock © esri"
Link to Athlone Lock © esri

MARINE NOTICE, No. 65 of 2022

Shannon Navigation

Athlone

Construction of pedestrian and cycleway bridge

Update on works

Waterways Ireland wishes to advise all masters of vessels and waterways users that the construction of the Athlone pedestrian and cycleway bridge commenced on 03 May 2022. The pedestrian and cycleway bridge will be built approx. 50 metres upstream of Athlone town bridge.
The navigation channel in the vicinity of the in-water works will continue to be restricted during the works. Large barges, workboats and other equipment will be operating in the navigation from Wansboro’s field (upstream of the Railway Bridge) to Athlone town bridge. Update on each Phase of the project is provided below.
Masters of vessels are advised to proceed with additional caution in the vicinity of the works and to follow the instructions of safety craft and personnel in the area.
Waterways Ireland thanks its customers for their cooperation.
Text Description automatically generated

P Harkin, Inspector of Navigation, 28 June 2022

Phase 1
Phase 1Installation of centre pier cofferdam. 15-18m Navigation Channel along West Bank

Phase2  Phase 2Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 3
Phase 3Temporary supports and centre pier in position from Mid-July. Navigation Channel reduced to approx. 15m

Phase 4
Phase 4Installation of centre bridge section Late-August. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 5
Phase 5
Installation of Eastern bridge section approx. Early September. Approx. duration of 3-4 days. Maintain 12-15m Navigation Channel along West Bank

Phase 6
Phase 6Installation of Western bridge section approx. Mid-September. Approx. duration of 3-4 days. Navigation Channel reduced to 10 – 12 metres adjacent to Centre Pier. One way system in operation for vessels.

Phase 7
Phase 7
Removal of temporary works from instream. Approx 1 week duration at end of September / early October. Open permanent 40 metre Navigation Channel along West Bank.

Athlone, Bau einer Fußgänger- und Radwegbrücke, Aktueller Stand der Arbeiten
Waterways Ireland möchte alle Schiffskapitäne und Wasserstraßennutzer darüber informieren, dass die Bauarbeiten für die Fußgänger- und Radwegbrücke in Athlone am 03. Mai 2022 begonnen haben. Die Fußgänger- und Radwegbrücke wird ca. 50 Meter stromaufwärts der Athlone Stadtbrücke gebaut.
Die Schifffahrtsrinne in der Nähe der Unterwasserarbeiten wird während der Arbeiten weiterhin eingeschränkt sein. Große Lastkähne, Arbeitsboote und andere Geräte werden in der Fahrrinne von Wansboro’s Field (flussaufwärts der Eisenbahnbrücke) bis zur Athlone Town Bridge verkehren. Im Folgenden finden Sie aktuelle Informationen zu den einzelnen Phasen des Projekts.
Die Kapitäne der Schiffe werden gebeten, in der Nähe der Arbeiten besonders vorsichtig zu fahren und den Anweisungen der Sicherheitsfahrzeuge und des Personals in diesem Gebiet Folge zu leisten.
Waterways Ireland dankt seinen Kunden für ihre Mitarbeit.
Text Beschreibung automatisch generiert

    • Phase 1
      Einbau eines Kofferdamms für die Mittelmole. 15-18m Schifffahrtskanal entlang des Westufers
    • Phase 2
      Provisorische Stützen und Mittelmole in Position ab Mitte Juli. Reduzierung der Fahrrinne auf ca. 15 m
    • Phase 3
      Temporäre Stützen und Mittelpfeiler ab Mitte Juli in Position. Verringerung der Fahrrinne auf ca. 15 m
    • Phase 4
      Einbau des mittleren Brückenteils Ende August. Dauer: ca. 3-4 Tage. Beibehaltung der 12-15 m breiten Fahrrinne am Westufer
    • Phase 5
      Einbau des östlichen Brückenteils ca. Anfang September. Dauer: ca. 3-4 Tage. Aufrechterhaltung der 12-15 m langen Fahrrinne entlang des Westufers
    • Phase 6
      Einbau des westlichen Brückenteils ca. Mitte September. Dauer: ca. 3-4 Tage. Verkleinerung der Fahrrinne auf 10 – 12 Meter neben der Mittelmole. Einbahnregelung für Schiffe in Betrieb.
    • Phase 7
      Beseitigung der provisorischen Arbeiten im Fluss. Ca. 1 Woche Dauer Ende September/Anfang Oktober. Eröffnung der permanenten 40 Meter langen Fahrrinne entlang des Westufers.

MARINE NOTICE, No. 55 of 2022

Shannon Harbour © esri
Shannon Harbour © esri
Mullingar Harbour © esri
Mullingar Harbour © esri

MARINE NOTICE, No. 55 of 2022

Grand Canal – Shannon Harbour & Royal Canal – Mullingar

IWAI Events June & July 2022

Waterways Ireland wishes to advise all users of the Royal Canal and Grand Canal of the following IWAI events;

      • Grand Canal – Shannon Harbour Canal Boat Rally – 24/25/26 June 2022
      • Royal Canal – Mullingar Harbour – Float to the Fleadh – 31 July to 07 Aug 2022

Please note, vessels attending these events are required to apply for a Visitors Permit, free of charge, before entering the canal network.
Masters of vessels are requested to proceed at slow speed and note any directions issued in the vicinity of the events.
Waterways Ireland thanks its customers for their cooperation in this matter.

Patrick Harkin, Inspector of Navigation, 09 June 2022

Shannon Harbour Canal Boat Rally
Shannon Harbour Canal Boat Rally
Mullingar Harbour – Float to the Fleadh
Mullingar Harbour – Float to the Fleadh

Grand Canal – Shannon Harbour & Royal Canal – Mullingar
IWAI Veranstaltungen Juni & Juli 2022
Waterways Ireland möchte alle Benutzer des Royal Canal und des Grand Canal auf die folgenden IWAI-Veranstaltungen hinweisen;

        • Grand Canal – Shannon Harbour Canal Boat Rally – 24/25/26 Juni 2022
        • Royal Canal – Mullingar Harbour – Float to the Fleadh – 31. Juli bis 07. August 2022

Bitte beachten Sie, dass Schiffe, die an diesen Veranstaltungen teilnehmen, eine kostenlose Besuchererlaubnis beantragen müssen, bevor sie das Kanalnetz befahren dürfen.
Die Kapitäne der Schiffe werden gebeten, mit langsamer Geschwindigkeit zu fahren und alle Anweisungen zu beachten, die in der Nähe der Veranstaltung ausgegeben werden.
Waterways Ireland dankt seinen Kunden für ihre Kooperation in dieser Angelegenheit.

Happy Saint Patricks Day

Many greetings for Saint Patrick’s Day
sends Captain’s Handbook © to the Irish island

Saint Patrick’s Day

Who was St. Patrick?

St. Patrick was born Maewyn Succat but changed his name to Patricius (or Patrick), which comes from the Latin term for ‚father figure‘ following his decision to become a priest.
The celebrations on March 17 first began back in 1631, when the Church created a Feast Day in homage to St. Patrick. Having been the Patron Saint of Ireland, he died around the fifth century, which means that his passing came 12 centuries prior to the modern version of the holiday first being observed.
„We know that he was a Roman citizen, because Britain was Roman then, and then he was enslaved and taken to Ireland, where he either escaped or was released,“ said Marion Casey, a clinical assistant professor of Irish Studies at New York University.
„And then he became a priest and went back to Ireland, where he had a lot of luck converting the Druid culture into Christians.“
The church associated a botanical item with St. Patrick, which is customary for all saints, as he was assigned him the symbol of the lucky shamrock.
The first New York City parade took place in 1762, and after the Irish Rebellion in 1798 the colour green became linked to the St. Patrick’s Day festivities.

Wer war St. Patrick?

Der heilige Patrick wurde als Maewyn Succat geboren, änderte aber seinen Namen in Patricius (oder Patrick), was vom lateinischen Begriff für „Vaterfigur“ abgeleitet ist, nachdem er beschlossen hatte, Priester zu werden.
Die Feierlichkeiten am 17. März begannen im Jahr 1631, als die Kirche einen Festtag zu Ehren von St. Patrick einführte. Er war der Schutzpatron Irlands und starb um das fünfte Jahrhundert, was bedeutet, dass sein Tod 12 Jahrhunderte vor der modernen Version des Feiertags liegt.
„Wir wissen, dass er ein römischer Bürger war, weil Britannien damals römisch war, und dann wurde er versklavt und nach Irland gebracht, wo er entweder entkam oder freigelassen wurde“, sagte Marion Casey, eine klinische Assistenzprofessorin für Irische Studien an der New York University.
„Dann wurde er Priester und kehrte nach Irland zurück, wo er viel Glück hatte, die Druidenkultur zum Christentum zu bekehren.
Die Kirche verband einen botanischen Gegenstand mit St. Patrick, wie es bei allen Heiligen üblich ist, da ihm das Symbol des glückbringenden Kleeblatts zugewiesen wurde.
Die erste Parade in New York City fand 1762 statt, und nach dem irischen Aufstand von 1798 wurde die Farbe Grün mit den Feierlichkeiten zum St. Patrick’s Day verbunden.

MARINE NOTICE, No. 04 of 2022

Sallins-Co. Kildare; © esri
Sallins-Co. Kildare; © esri

MARINE NOTICE, No. 04 of 2022

Grand Canal

Sallins, Towpath Closure

15 to 26 February 2022

Waterways Ireland wishes to advise that the towpath on the South Bank of the Grand Canal adjacent to Church Avenue will be closed from 15th to 26th February 2022. This closure is to facilitate tree removal works for the new Greenway route.
Waterways Ireland apologies for any inconvenience caused.

P Harkin, Inspector of Navigation, 02 Feb 2022

Sallins Harbour Grand Canal
Sallins Harbour Grand Canal

 Sallins, Sperrung des Treidelpfades, 15. bis 26. Februar 2022
Waterways Ireland möchte darauf hinweisen, dass der Treidelpfad am Südufer des Grand Canal in der Nähe der Church Avenue vom 15. bis 26. Februar 2022 gesperrt wird. Die Sperrung erfolgt, um Baumfällarbeiten für die neue Greenway-Route zu ermöglichen.
Waterways Ireland entschuldigt sich für die entstandenen Unannehm-lichkeiten.

MARINE NOTICE, No. 91 of 2021

Bellanaleck Marina Area Carrick Craft;© esri; click picture to Arcgis Erne Map
Bellanaleck Public Jetty; © esri

MARINE NOTICE, No. 91 of 2021

Erne System

Bellanaleck slipway

Closed until further notice

Waterways Ireland wishes to advise Master of Vessels on the Erne System that Bellanaleck slipway is closed until further notice. A further Marine Notice will be issued when the slipway is reopened.
Waterways Ireland thanks all waterways users for their understanding in relation to this matter.

Patrick Harkin, Inspector of Navigation, Waterways Ireland, 23 December 2021

Anleger (Slipway) von Bellanaleck
Anleger (Slipway) von Bellanaleck
Anleger (Slipway) von Bellanaleck
Anleger (Slipway) von Bellanaleck

Slipanlage Bellanaleck, bis auf Weiteres geschlossen
Waterways Ireland möchte die Kapitäne von Schiffen auf dem Erne System darauf hinweisen, dass die Slipanlage am Public Anleger Bellanaleck bis auf weiteres geschlossen ist. Sobald die Slipanlage wieder geöffnet ist, wird eine weitere Bekanntmachung herausgegeben.
Waterways Ireland dankt allen Wasserstraßenbenutzern für ihr Verständnis in dieser Angelegenheit.

Captain's Handbook ©
Datenschutz-Übersicht

Diese Website verwendet Cookies, damit wir dir die bestmögliche Benutzererfahrung bieten können. Cookie-Informationen werden in deinem Browser gespeichert und führen Funktionen aus, wie das Wiedererkennen von dir, wenn du auf unsere Website zurückkehrst, und hilft unserem Team zu verstehen, welche Abschnitte der Website für dich am interessantesten und nützlichsten sind.

Die Datenschutzerklärung finden Sie  hier ====>>

This website uses cookies so that we can provide you with the best possible user experience. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website, and helps our team understand which sections of the website are most interesting and useful to you.

The privacy policy can be found  here ====>>