NEWCOMEN BRIDGE LIFT DATES 2023

Waterways Ireland wishes to advise that the provisional schedule of bridge lift dates 2023 for Newcomen Bridge, Royal Canal, Dublin is as follows:

Date Day Times Time of LowWater
30th April Sunday 9am-1pm 1456
27th May Saturday 9am-1pm 1159
27th June Tuesday 11am-1pm 1256
27th July Thursday 11am-1pm 1252
29th August Tuesday 11am-1pm 1642
26th September Tuesday 11am-1pm 1538

NOTES:

        • Arrangements have been made for Iarnród Éireann to open the bridge on the above dates / times, if there is demand.
        • Waterways Ireland Eastern Regional Office (Tel: +353(0)1 868 0148 or dublincanals@waterwaysireland.org ) require 2 weeks’ notice from boaters for use of these lifts. Should there not be a demand (min 2 boats) for a particular date, Iarnród Éireann will be notified by WI that the scheduled lift is cancelled.
        • A maximum number of boats passing will be implemented to keep to the times given above for the planned lifts (16 for the Sat / Sun lifts & 8 for the weekday lifts). Priority will be given on a first come first served basis.
        • On day of lift, boaters and passengers must follow guidance from Waterways Ireland staff about sequence of passage under bridge & through Lock 1.

Waterways Ireland thanks its users for their understanding in this matter.

P Harkin, Inspector Of Navigation, Waterways Ireland, 14 April 2023

Railway Bridge; © Joe Treacy
Railway Bridge; © Joe Treacy
Railway Bridge; © Joe Treacy
Railway Bridge; © Joe Treacy

Royal Canal, Dublin Hebetermine der Newcomen-Brücke 2023
Waterways Ireland möchte darauf hinweisen, dass der vorläufige Zeitplan für die Hebung der Newcomen Bridge, Royal Canal, Dublin, im Jahr 2023 wie oben in der Tabelle aussieht.

ANMERKUNGEN:

        • Es wurden Vorkehrungen getroffen, dass Iarnród Éireann die Brücke zu den oben genannten Daten / Zeiten öffnen kann, wenn eine entsprechende Nachfrage besteht.
        • Waterways Ireland Eastern Regional Office (Tel: +353(0)1 868 0148 oder dublincanals@waterwaysireland.org) verlangt von den Bootsfahrern eine Vorankündigung von 2 Wochen für die Nutzung dieser Lifte. Sollte für ein bestimmtes Datum keine Nachfrage (mindestens 2 Boote) bestehen, wird Iarnród Éireann von WI benachrichtigt, dass der geplante Lift abgesagt wird.
        • Um die oben genannten Zeiten für die geplanten Lifte einzuhalten, wird eine Höchstzahl von Booten festgelegt (16 für die Sa/So-Lifte und 8 für die Wochentagslifte). Die Priorität wird nach dem Prinzip „Wer zuerst kommt, mahlt zuerst“ vergeben.
        • Am Tag der Aufhebung müssen Bootsfahrer und Passagiere die Anweisungen der Mitarbeiter von Waterways Ireland zur Reihenfolge der Durchfahrt unter der Brücke und durch Schleuse 1 befolgen.

Waterways Ireland dankt seinen Benutzern für ihr Verständnis in dieser Angelegenheit.

 

MARINE NOTICE 029 of 2016

Newcomen Bridge Royal Canal © esri maps; click to " esri maps Newcomen Bridge Royal Canal"
Newcomen Bridge Royal Canal © esri

MARINE NOTICE, No 29 of 2016

ROYAL CANAL DUBLIN

NEWCOMEN BRIDGE

LIFT DATES 2016 – update

The schedule of Newcomen Bridge lift dates for 2016 is now updated. Planned lifts after June have had to be cancelled until necessary upgrade works are completed. A further Marine Notice will issue to advise.

Thursday 14th April  11am – 1pm
Sunday 1st May  9am – 1pm
Saturday 28th May  9am – 1pm
Tuesday 14th June  11am – 1pm

Notes:

  1. Arrangements have been made for Irish Rail to open the bridge on the above dates / times, if there is demand.
  2. Waterways Ireland Eastern Regional Office (tel: +353(0)1 868 0148 or dublincanals@waterwaysireland.org) require 2 weeks’ notice from boaters for use of these lifts; should there not be demand (min 2 boats) for a particular date, Irish Rail will be notified by Waterways Ireland that this lift is cancelled.
  3. A maximum number of boats passing will be implemented to keep to the times given above for the planned lifts (16 for the Sat / Sun lifts & 8 for the weekday lifts)
  4. On day of lift, masters and their crew must follow guidance from Waterways Ireland staff about sequence of passage under bridge & through Lock 1, and must remain within signed and designated areas.

C.J.Lawn, Inspector of Navigation, 30 March 2016

Railway Bridge; © Joe Treacy
Railway Bridge; © Joe Treacy

MARINE NOTICE 134 of 2015

Newcomen Bridge Royal Canal © esri maps; click to " esri maps Newcomen Bridge Royal Canal"
Newcomen Bridge; © esri

MARINE NOTICE, No.134 of 2015

ROYAL CANAL

Dublin

Notice of Bridge Lift – Newcomen Bridge

Waterways Ireland wishes to advise masters and owners of vessels that a final 2015 Newcomen Bridge Lift has been arranged for Thursday 29th October 2015.

Works are ongoing to repair Spencer Dock Sea Lock (refer Closure Notice MN86/2015) but, as this is yet incomplete, navigation through the Lock and Dock area is only possible at particular stages of the tide. For this bridge lift date, the tide times are only suited to travel in a westward direction outbound from Dublin.

Should anyone wish to avail of the above arrangement please contact Waterways Ireland (tel: +353(0)1 868 0148 or email dublincanals@waterwaysireland.org) by Tuesday 27th October to register your interest, and times of passage will be advised.

Charles Lawn, Inspector of Navigation, 19 October 2015.

Railway Bridge; © Joe Treacy
Railway Bridge; © Joe Treacy

MARINE NOTICE 009 of 2015

Newcomen Raiway Bridge © esri
Newcomen Raiway Bridge © esri

MARINE NOTICE, No 9 of 2015

NEWCOMEN BRIDGE LIFT DATES   2015

Royal Canal Dublin

The schedule of lift dates 2015 for Newcomen Bridge, Royal Canal, Dublin and associated details are given below:

 Monday 27th April  11am – 1pm
 Sunday 3rd May  9am – 1pm
 Saturday 30th May  9am – 1pm
 Thursday 11th June  11am – 1pm
 Thursday 9th July  11am – 1pm
 Thursday 23rd July  11am – 1pm
 Monday 24th August  11am – 1pm
 Monday 24th August  11am – 1pm
  1. Arrangements have been made for Irish Rail to open the bridge on the above dates / times, if there is demand.
  2. Waterways Ireland Eastern Regional Office (tel: +353(0)1 868 0148 or dublincanals@waterwaysireland.org) require 2 weeks’ notice from boaters for use of these lifts; should there not be demand (min 2 boats) for a particular date, Irish Rail will be notified by WI that this lift is cancelled.
  3. A maximum number of boats passing will be implemented to keep to the times given above for the planned lifts (16 for the Sat / Sun lifts & 8 for the weekday lifts)
  4. On day of lift, boaters and passengers must follow guidance from Waterways Ireland staff about sequence of passage under bridge & through Lock 1, and must remain within signed and designated areas.

C.J.Lawn, Inspector of Navigation, 26 February 2015